Shettleston Housing Association

House construction
and the subsequent occupation of homes are recognised as major contributors
to pressing environmental problems. Recent studies have shown that environmentally
sustainable housing can bring large scale reductions in the environmental
burden of housing and economic savings for landlords and tenants with
only a relatively small increase in capital costs.
Of the total
amount of energy used in a typical house (excepting embodied energy costs),
61 per cent goes on space heating, 22 per cent on water heating, 7 per
cent on cooking and 10 percent on lights and appliances.
Our main aim
in the Shettleston proposal has been to reduce tenants running costs whilst
ensuring that the construction of the houses and selection of materials
takes into account the full implications of their energy lifecycle. Our
approach to sustainability was developed along four main approaches:
First
of all in the production of the houses: by providing a high level of thermal
insulation, reducing air infiltration and careful selection of the materials.
Secondly
by making use of geothermal energy combined with supplementary solar panels
to provide inexpensive heating.
Thirdly
by the house designs themselves: by allowing greater internal flexibility,
barrier free standards to the layout, allowing for secondary uses of loft
spaces, creating a varied mix of house types, from family, to young person
and to elderly, along with wheelchair use.
Fourthly
by creating an environment which is sustainable, a car free scheme which
increases safety for children, selection of plants which bring life and
colour to the surroundings.
Each of these
approaches is discussed in greater detail below. Clearly there were problems
in achieving our aims within the budget constraints imposed by mainstream
social housing. Some compromises have had to be made to meet the budgets,
but the main elements of the project were all retained and the project
is now on site. Completion is due in April 1999.
We have also
been successful in obtaining an additional grant from Forward Scotland
to cover some of the Solar panel installation and the grey water recycling
system.
House production
We have chosen
to construct the houses from timber as far as possible. The use of a webbed
timber beam allowed us to provide thick wall insulation and reach U values
which are under 0.2Wm2Cº. The panels are filled with warmcell insulation
which is made from recycled newspaper. The wall panels will be largely
prefabricated apart from the external and internal skins. Prefabrication
will speed the on site construction time and allow greater control over
critical elements of the structure.
The floors
are also in webbed timber beams and where possible span between crosswalls.
The roof also uses webbed beams to form a 300mm thick fully insulated
roof, spanning between ridge and eaves. Originally we planned to use Masonite
beams which because of their construction, were deemed the most environmentally
friendly. However the contractor chose to use Truss Joist Macmillan to
supply the webbed beams. The change did affect the overall insulation
slightly and we acknowledge that the TJM beam uses a small amount of glue
in its construction, although it does make use of recycled timber chippings.
The floor
construction is a concrete slab. We originally planned to have a timber
finished floor, but altered to have a screed finish due to cost constraints.
This provides a certain level of heat capacitance and allows us to provide
floors which are level with the external paths.
The wall construction
uses the breathing wall technique pioneered by Warmcell.

The components
of the wall are selected with the correct vapour resistance to allow vapour
to diffuse through the structure without the risk of interstitial condensation.
We have still included a vapour barrier (BSK410) to compensate for the
vapour resistance of the panelvent. Because the warmcell is applied in
sprayed form between the structural studs, all voids are fully filled.
This provides much better air tightness of the structure reducing air
leakage resulting in further energy savings.
We have also
allowed for a "services" zone in the internal face of all external
walls and in kitchen walls.
The external
skin is either brick, larch weatherboarding or a render system applied
to a calcium silicate board panel.
Materials
have been selected by considering the impact throughout their whole life
cycle: during the extraction phase, the production phase, building phase,
occupational phase and decomposition phase. The main issues considered
in the assessment were:
the
shortage of raw materials (there is a finite resource for many of them,
hence our emphasis on using recycled materials)
the
ecological damage caused by extraction of the raw material
the
energy consumption at all stages (including transport- we have tried to
select materials which can be as locally sourced as possible)
water
consumption
noise
and odour pollution
harmful
emissions, such as those leading to ozone depletion
global
warming and acid rain
health
aspects
repairability
reusability
waste
produced
Some compromises
have had to be made on cost grounds, for example, we have specified some
small areas of zinc roof sheeting, ideally we would have preferred copper
sheet because of its much longer life and greater ability to be recycled.
We did investigate the use of aluminium sheet made from recycled aluminium
cans, but this did not seem to be possible for very small quantities.
A number of
"recycled" materials will be used:
Insulation
material from recycled newspaper.
Recycled
brick from the actual site has been used for the boundary wall butt and
environmental work.
Recycled
stone sets and paviours for the front garden areas. Recycled concrete
paviours for the rear backcourts- (these are from adjacent sites and presently
in storage).
Some
recycled floor timbers, these boards had been kept in store by the Association,
they did not have to be de-nailed or cleaned.
Some
bathroom fittings from houses being demolished by another Housing Association
are being used in two houses and some steel baths are being re- used.
Some
of the front railings are being recycled from backcourts in Maryhill.
We did have
problems in trying to get the Contractor to think seriously about recycling
materials. Because they could not clearly identify the costs or sources,
it became difficult for them to cost the work. They were also worried
about liability, particularly when we located a source for concrete roof
tiles. In this case we had sourced a number of tenements in Drumchapel
which were about to be demolished, but demolition contractors said that
it would cost too much to remove the tiles carefully because of the additional
edge protection and safety measures that would be required. We finally
opted for a new concrete roof tile produced in Scotland.
We also tried
to source recycled brick in Scotland, but had no luck in doing so. We
did locate such brick in the South of England but it did not make practical
sense to transport it up to Scotland.
Untreated
materials which use less, or preferably no, glue or chemicals, and exclude
PVC, have been preferred, in summary:
Orientated
strand board for some wall sheathing and webbed beams.
Larch
battens and counterbattens avoid the need for chemical preservation treatment.
Larch
weather boarding applied externally will be untreated, available from
Perthshire.
Timber
windows and other water sensitive timbers to be treated with Boron preservative,
not CCA.
Untreated
softwoods in preference to MDF cill boards, skirtings.
High
Density Polyethylene HDPE pipe for drainage within houses and for downpipes,
instead of uPVC.
Low
odour paints and stains which are resin oil based with no toxic emissions
from biocides
Finding an
alternative to PVC was difficult and in the end we have had to resort
to PVC gutters. We had quite some discussion over the merits of HDPE pipe.
Whilst it does not use PVC, it needs to be installed using a special jointing
system which makes it more difficult to dismantle in the future. However
we still plan to use it for rain water pipes but eventually had to resort
to PVC pipes for internal soil pipes.
We did investigate
larch windows which were very environmentally friendly, unfortunately
costs were too high for this project.
Getting timber
to be Boron treated proved to be very difficult. There is only one sawmill
in Scotland which does this and timber would have had to have been transported
to Inverness for treatment. In the end we resorted to a water based aqua
vacvac treatment for those timbers which required treatment, but kept
the treatment down to a minimum.
Materials
which have a relatively low embodied energy:
concrete
roof tiles instead of clay tiles, use slightly less energy. We have decided
not to use recycled Scottish Slate, since the material is not being replenished
and such demand only results in buildings in remote country areas being
stripped to meet the demand. If there was a Scottish slate quarry in operation
we would have considered it.
Brass
ironmongery was considered instead of aluminium, but in the end we chose
aluminium ironmongery made in the UK rather than opt for imported brass.
Larch
weather boarding in preference to western red cedar which is largely imported
windows
and doors made from softwoods derived from sustainable sources
(most
of the materials noted above)
Heating and Ventilation system
After initial investigations
of the site history it was discovered that a disused coalmine exists deep
underground. We have devised a scheme in association with "enconsult"
which uses the preheated water in the flooded coalmine to heat the houses.
The calculation for the
SAP rating resulted in a figure of 125 (to round down to 100) which is
exceptionally high.
It is worked out for a
ground floor flat and would result in an estimated annual heating bill
of £19.33p with water heating at £55.48, although this figure could be
reduced further if a commercial fuel tariff was used. The figure for heating
does not take into account any solar pre-heated of incoming ventilated
air, which could reduce costs still further.
The heating system is illustrated
in the attached diagram.

The system works as follows:
The water in the coalmine,
which is 100 metres below ground level, will be at a temperature of about
12ºC throughout the year. This water is heated by geothermal action from
the planets molten core and will last the life of the planet. A well hole
has been drilled down to the mine and an in-line pump will then pump the
warmed water through a heat pump, boosting the temperature to 55ºC. There
are two heat pumps which function at off peak periods to make use of economy
2000 tariff. The water will be stored in a large, well insulated, thermal
storage tank and the warm water will then be distributed to each house
to provide heating to radiators. Each flat will have its own thermostat
and timer switch. Low temperature heating is entirely appropriate for
well insulated properties, as there is no need for large heat inputs and
the risks of scalding by touch are eliminated.
Hot Water
The water in the thermal
store is pumped through indirect coils in each hot water cylinder in order
to heat the water to 45ºC. Although warm water can be taken from the cylinder,
we are providing electric immersers so that tenants who require higher
temperatures for washing dishes etc., can boost the temperature of water
in the cylinder. The energy required to raise water from 45ºC to 60ºC
is much less than a system which heats water from a cold start.
Heating and hot water would
be charged as a service charge as part of the rent, although the actual
running costs are expected to be very low. The advantage in having tenant
control over heating the hot water is that expensive metering controls
are avoided.
In addition, a solar roof
has been designed immediately above the thermal store.
The roof is South facing,
pitched at a designed 35ºC and will provide a solar panel with a total
area of 36m2. The solar panels will provide additional heating to the
thermal storage tank, mostly during the afternoon when a large part of
the tanks heat will have been dissipated.
Water supply
Domestic cold water will
come from the mains supply. However cooled water from the heat pumps is
a by product of the geothermal arrangement and we will take this cold
water into a large storage tank and then feed the WC cisterns in all the
houses. Such water can also be pumped to the small water feature in the
front garden. Residual water from the geothermal supply needs to be discharged
back into the ground at a point below the water table.
Ventilation
Because of the air tightness
of the dwellings, we have incorporated a simple ventilation system in
the four terraced houses which will take pre-heated air from the void
between roof tiles and sarking and pressurise the houses slightly. This
has the effect of reducing draughts as well as making use of solar pre-heat
to the incoming air. Air quality is greatly enhanced.
The majority of the houses
also rely on passive stack ventilation systems for kitchens and bathrooms.
House design and layout
The houses are laid out
to make maximum use of this tight site. They are largely orientated East
West giving good daylight to both front and back gardens. In total there
are 16 dwellings, providing a variety of types and sizes, but designed
to cater for families, young couples and the elderly.
In all cases buffer draught
lobbies have been created to reduce energy losses and create additional
storage and utility rooms. Living rooms open into the kitchen and dining
area, allowing ease of movement between the spaces. A ground floor toilet
is also provided to the terraced houses, capable of taking a wheelchair
for any visitors, or indeed future use by an occupant. The straight stair
could have a stair lift fixed to it. Different layouts are possible on
the ground floor and two options are shown. Upstairs there are three bedrooms
with built in storage.
The roof structure is trussless
and allows the loft space to be floored and used as storage. It would
be accessed by a Ramsay ladder. A fixed stair could be installed but more
onerous regulations then come to play. The attic room is high enough to
stand in and has a skylight.
The single entrance flats
use a similar device on the top floor, except that we have shown the loft
space as a gallery deck which opens into the living room area.
There is a shared external
stair at the rear which provides the upstairs flats with access to the
back garden.
The corner flats are accessed
from a glazed atrium, designed to bring light and space into the main
circulation area. The principle being that elderly people can meet in
this space, and even sit and pass the time with their neighbours. Flats
at street edge all achieve some Southern light, and privacy is obtained
by raising the floor level above the street level.
There is a single wheelchair
flat which has its own entrance and car bay. It is designed for wheelchair
circulation and connects through into the close so that communication
with neighbours is maintained. The access into the close is not to ideal
disabled standards due to the tightness of space.
Environment
The site is close to shops
and public transport. A decision was taken after discussion with local
planners that a car free scheme would be most appropriate for the site.
We have therefore designed
a scheme as "car free", providing only 4 on street car bays,
made on the existing road line, as well as an individual bay for use in
the wheelchair standard house. Making the scheme car free allows the creation
of a semi private front garden space which gives the houses added privacy,
better security, increased safety for children and a much more pleasant
environment. Discussions are continuing with the Roads Department and
Planning so that a workable legal agreement can be drawn up to ensure
tenants within the scheme do not own, or have access to a car. The four
visitor bays will be marked as residential parking for visitors only,
with the aim of deterring parking by drivers unconnected with the scheme.
The front area is screened
from the street by a low hedge, deep in character, with trees showing
their trunks above and a canopy which allows clear views under tree and
over hedge. One entrance is provided through a pergola. A semi public
gravel path leads to each of the individual houses, with the route passing
a small water feature.
Each house and flat has
its own private space as well, screened by wicker fencing. Binstores are
provided in screened areas to the house fronts. In the corner flats bins
are located to the rear of the properties.
Wall surfaces are provided
with cable stays for wire trellis work which will take a selection of
creepers and wall friendly plants. Such growth will provide additional
protection to the walls as well as reducing noise levels and creating
a more pleasant climate.
Downpipes at the rear have
water barrels to provide water for gardening and space has been provided
for composting of plant debris.
Deep plant beds have been
provided in the atrium space so that climbers and vines can grow up to
the second floor, both at the glazed front and around the stairwell. They
will be fed by water from the cold water storage tank.
Refuse recycling
We are presently developing
a scheme which will encourage waste separation and waste recycling within
the scheme.
Client Group Involvement
The house designs have
been developed after meetings with the Housing Associations Development
Committee. A Tenants sub group was set up to develop some of the sustainable
themes, with the aim of encouraging an understanding of the issues involved.
In addition to regular
design meetings attended by the Association and its consultants, a special
technical seminar was held and a number of other Housing Associations
invited to attend, including representatives from Planning and Building
Control. Issues discussed included the breathing wall system, under floor
heating, material selection for sustainability and geothermal energy.
The seminar produced a lot of useful feedback from those that attended.
There were also in-house
meetings to explain to all Housing Association staff what the aims of
the housing proposal were. Maintenance staff contributed to the specification
of materials and set about collecting materials from other sites which
could be used in the project.
Comments on Structure
Reasonable soil conditions
are to be found over the site at shallow depth below the existing ground
surface. This has permitted the use of a concrete beam foundation cast
integrally with the ground slab, thus dispensing with the need for underbuilding
walls.
The choice of timber frame
for the flats and terraced houses reflects the architectural requirements
for high insulation values and allows much of the structure to be prefabricated.
This will lead to improved quality control and speed of construction.
Architects on the project were
John Gilbert Architects.
Sustainable Housing for everyone?
We do not
presume that the Shettleston scheme is the answer to sustainable housing.
It will however demonstrate some of the techniques which sustainable developments
must take on board. We have learnt a lot in developing the ideas for this
unique project and hope to be able to incorporate many of the ideas in
other new build and rehabilitation projects.